Transport Schemes in Stratford-upon-Avon Supplementary Planning Document Consultation

The information provided on this webpage is to inform the public consultation currently being undertaken by Stratford on Avon District Council on the proposed amendments to the Supplementary Planning Document.

A number of documents and cost estimates have been provided to support the amendments proposed to the List of Schemes that is contained within the Supplementary Planning Document. A detailed description is provided with each document or cost estimate:

1. Birmingham Road Cycle Scheme Extension to Bishopton Island

The cost of this scheme was updated from the original scheme design & estimate produced by the County Council in 2005. Costs were updated with those recently incurred on other similar schemes within Warwickshire.

Birmingham Road Cycle Route Extension Costs

Birmingham Road Cycle Route Extension Design

2. Birmingham Road to Alcester Road Pedestrian / Cycle Bridge

The cost of this scheme was updated from the original scheme design & estimate produced by the County Council in 2003. Costs were updated with those recently incurred on other similar schemes within Warwickshire.

Bham Road Alcester Road Ped Cycle Scheme Design 2003 Cost Estimate

Bham Road to Alcester Road Ped Cycle Scheme Design

Birmingham Road to Alcester Road Ped Cycle Link Cost Estimate 2011

3. Birmingham Road Traffic Management Scheme Feasibility Study

The cost estimate for this study was benchmarked against the cost of the recently completed Stratford Bus Station study, which is of a similar size, scale and scope to that envisaged for the Traffic Management Scheme:

Stratford Bus Station Final Report July 2011

4. Stratford Parkway Station

Due to the commercial sensitivity of costs associated with the new Stratford Parkway Station, the cost estimate has been benchmarked against the outturn cost for Coleshill Parkway Station (similar scheme completed in 2007):

Stratford Parkway Station Benchmarked Costs 2011

5. Rother Street & Market Area Traffic junction Enhancement – Shared Space Feasibility Study

The cost estimate for this study was benchmarked against the cost of the recently completed Stratford Bus Station study, which is of a similar size, scale and scope to that envisaged for the Shared Space Feasibility Study:

Stratford Bus Station Final Report July 2011

6. Stratford Cycle Projects

The cost estimate was developed from the Action Plan proposed by the Stratford Cycle Forum, using costs from recently completed similar schemes in Warwickshire.

Stratford Cycle Project Action Plan

Stratford Cycle Projects Cost Estimate

7. Stratford Southern Park & Ride

The cost estimate for the Southern Park & Ride was based on the outturn cost of the Northern Park & Ride scheme plus a contingency for risk.

Stratford Southern P&R Cost Estimates

8. Stratford Station Access Improvement Scheme

The cost estimates have been developed and updated from the Station Masterplan that was produced by consultants Arup in 2007.

Stratford Town Station Improvements Final Report

Stratford Town Station Access Improvement Scheme Cost

9. Stratford Station to Rother Market Enhancement Scheme

Cost estimate based on those incurred for other recently completed schemes in Warwickshire.

Stratford Station to Rother Market Cost Estimate

10. Stratford Historic Spine Scheme

Costs for this scheme were originally taken from the World Class Stratford ‘Walkable Core’ Study.

A cap on expenditure was then imposed by Stratford-on-Avon Area Committee in January 2011 as recorded in the minutes of the Area Committee meeting

Further information can  be obtained from:

John Harvey (Senior Transport Planner)

Warwickshire County Council

Tel: 01926 410410

Email: tpu@warwickshire.gov.uk